We are currently doing the plastering to the new build section. First fix M&E is finished, and the roof is 95% complete. Aluminium fascias are in progress, and all windows are fixed. The refurbishment of the existing school is being carried out in sections to keepp classroom sapace available. Four classrooms are finished, three are in progress, an three more to be commenced.
All the subcontractors have done a sterling job. IES Online are doing the heating and electrical, and doing a first class job. Allied Glazing from Sheffield are working for me for the first time, and have been exceptional, and joiners D&P Mitchell are performing at the same high standard that I've come to expect from them.